Assembly & installation
Installing a distribution board
From enclosure and DIN rail to circuit diagram and labelling
The distribution board is the heart of the installation, where the protective devices are gathered. A tidy, correctly labelled and documented board is both a legal requirement and a prerequisite for safe fault-finding later.
Choose and position the enclosure
Choose a flush-mounted or surface-mounted enclosure with a sufficient number of modules and an ingress protection rating (IP) that suits the surroundings. Position the board with clear operating space and access so it can be operated and maintained safely.
Plan the circuit layout
Fix the circuit diagram before you install: number of circuits, which loads belong to each, number and type of RCDs and the fuse characteristic (B/C/D). New homes must have at least 2 RCDs of type A with max. 30 mA.
New homesmin. 2 × RCD type A, 30 mAMount the breakers on the DIN rail
Clip the main switch, RCDs and circuit breakers onto the DIN rail in the planned order. The characteristic is chosen according to the load: B for lighting and sockets, C for motors and many electronic power supplies, D for heavy inrush currents.
Connect with a busbar (phase comb)
Use a busbar (phase comb) to connect the breakers' terminals efficiently rather than loose pieces of wire. Choose the number of poles (1-, 3- or 4-pole) according to the board's layout, and cut the busbar to length so that no bare teeth are left exposed.
Connect conductors with the correct colours
Connect the circuits according to the circuit diagram using the harmonised conductor colours (HD 308 S2): protective conductor PE green/yellow, neutral (N) blue, and line (L) brown, black or grey. Tighten all terminals to the specified torque.
PEgreen/yellowNblueLbrown/black/greyLabel circuits and board unambiguously
Label each circuit so it is clear what it supplies, and place an accurate circuit diagram in or by the board. Unambiguous labelling is a requirement at inspection and makes later fault-finding quick.
Verify before energising
Carry out inspection and testing (continuity, insulation resistance, RCD test, polarity, phase sequence) on the board before it is energised. Hand over an up-to-date circuit diagram and verification report at handover.
Take a photo of the finished, labelled board for the documentation — it saves time at the next service visit.
Source
Based on the DS/HD 60364 series and HD 308 S2 (cable colours) and the trade's product range (distribution board, busbar) and template »new domestic installation«.
Videos from NDLA
Video guide· Norwegian speech
Fordeling
Source
NDLA
«Fordeling» · Creator: Esteban Panza
License: CC BY-SA 4.0 · Original at NDLA ↗
Shown unaltered in the original language with the source's own subtitles. The video shows Norwegian practice — the method is often the same, but rules and standards may differ from the Danish ones.