A simple foundation or slab pour is geometrically a box — but the formwork must stand plumb and braced, the volume is calculated in advance, and the concrete is ordered in one go so the pour can be carried out without an unwanted cold joint. The guide follows the work from setting out to finishing. The concrete's strength, exposure class, reinforcement and cover are design matters.
Set out and check the diagonals
Measure and set out the foundation lines from one fixed starting point, and check squareness by measuring the two diagonals — if they are equal, the figure is square. Use the 3-4-5 method to set the right angles. A skewed setting-out here carries through the rest of the building.
Excavate to firm ground
Excavate to a firm, load-bearing base at the depth and width specified by the project. The bottom must be load-bearing and free of loose soil and water so the foundation does not settle. Frost-free depth and bearing capacity are design requirements — follow the drawing.
Erect the formwork plumb and braced
Set the formwork plumb and brace it firmly so that it can hold the concrete pressure without bowing out — fresh concrete is heavy and presses hard on the sides. Check plumb, alignment and internal dimensions, and that the formwork is tight so that cement slurry does not leak out.
Never underestimate concrete pressure — formwork that bows during casting cannot be straightened afterwards.
Calculate the volume and order including waste
Calculate the concrete volume as V = L · B · H with all dimensions in metres so the result is in m³, and add a waste allowance for excavation tolerance, overfill and shrinkage. Order the concrete in one go so the whole pour can be done in one operation without a construction joint. Several strips/points are calculated as separate volumes and added together. Use the «Concrete volume» calculator.
VolumeV = L · W · HLay the reinforcement with the correct cover
Lay the reinforcement according to the structural calculation and maintain the specified cover with spacers, so the reinforcement sits at the right height and is fully surrounded by concrete. Cover, amount of reinforcement and placement are design conditions — look them up, do not guess them.
Cast, compact and screed
Place the concrete, compact it (poker vibrator or tapping) so air pockets disappear and the concrete closes tightly around reinforcement and formwork, and screed the surface to the required level. Good compaction is essential for both strength and durability.
Cure and protect during the hardening period
Protect the fresh concrete against drying out too quickly, sun, rain and frost during curing — e.g. by covering or watering. Concrete that dries too quickly or freezes early does not reach its strength. Only strike the formwork when the concrete has sufficient strength according to the project's instructions.
Source
Based on Discebo's carpentry template «Process: formwork and concrete pouring», the article «Concrete volume — calculate the volume» and the calculation module's concrete volume (V = L · B · H · (1 + waste%)).
Videos from NDLA
Video guide· Norwegian speech
Jernbinding høgrehendt
Source
NDLA
«Jernbinding høgrehendt» · Supplier: Kjell Brørs
License: CC BY-SA 4.0 · Original at NDLA ↗
Shown unaltered in the original language with the source's own subtitles. The video shows Norwegian practice — the method is often the same, but rules and standards may differ from the Danish ones.